Impact of Newer Technologies on Construction Projects

Corey Zussman

Corey Zussman

As a young architect starting my career, I was tasked with construction observation. My equipment consisted of a tape measure, one half-size set of construction documents, a legal pad, and a pen.  If I was lucky, I was occasionally able to use the company film camera. As the years went on, I requested a digital camera for my reviews, which I had to earn by producing a punch list on a specific project that numbered more than 500 items. Needless to say, I apologized to the contractor ahead of time and earned my digital camera.

The camera changed my approach to reviews and the quality of information I was able to deliver to the contractor. The reports were easier to understand, which generated quicker responses. However, as projects increased in complexity and staff sizes decreased, projects were getting harder to properly monitor.  We needed to do more with less. While the photos were better at explaining the condition in question, they did not improve the construction process. I knew that I needed to find better tracking abilities and a way to leverage all our construction projects to better understand what was happening. Without proper data management, I could not determine what issues were being repeated throughout the company, lessons learned or how we could improve.

Over my 30-year career, my roles and responsibilities have evolved. I have served as an owner's representative, a developer and now, a contractor, as the Director of Quality Management.

A construction monitoring program allows contractors to explore new and exciting ideas that are emerging every day and evaluate the intent of these ideas with overall goal of building effectively

My current role requires me to actively track more than 30 projects concurrently, and between 50-75 projects annually for a large commercial contractor in Chicago. We construct in every market, from small interior projects to very large entertainment venues and high-rise buildings.As you could imagine, construction monitoring for all these projects takes a smooth process, contractors who understand the details before they get to the jobsite and continuous improvement throughout the entire system.

While the industry average for correcting installations ranges between 3 percent and 5 percent of project cost, our average rework cost is 0.37 percent, which is almost 10x less than the industry average. Our record is a direct result of effective pre-installation meetings and the construction monitoring tools we use.

The Role of Pre-installation Planning

We have found the best way to monitor construction is to prepare the team before they are on site. We do this through pre-installation meetings with the trades and by ensuring that the drawings are correct with regard to sequencing, compatibility and coordination. This allows questions to be asked and addressed ahead of time, which results in better installations and makes construction monitoring more efficient.

Leveraging Construction Monitoring Technology

Our monitoring system reduces cumbersome procedures and scales to fit the needs of each project. During the pre-installation planning, we reference our construction monitoring information and use new tools such as 3D printed models and 3D PDFs to better examine specific details in a more productive manner.